In PPBE, which phase is primarily responsible for translating the strategic plan into a prioritized set of programs?

Prepare for the Certified Defense Financial Manager Exam 1. Study with flashcards and multiple choice questions. Each question includes hints and explanations to boost your knowledge. Ace your exam with confidence!

Multiple Choice

In PPBE, which phase is primarily responsible for translating the strategic plan into a prioritized set of programs?

Explanation:
In PPBE, translating the strategic plan into a prioritized set of programs happens during the programming step. This phase takes the strategic guidance and capability needs identified in planning and develops concrete program proposals, weighing options and trade-offs within the available resources. The output is a prioritized portfolio of programs, typically documented in the Program Objective Memorandum and the Future Years Defense Program, which specifies what will be funded and in what order over multiple years. Budgeting then assigns dollar amounts to those programs, and execution carries them out. So the programming phase is the one that converts strategy into an ordered, fundable set of programs.

In PPBE, translating the strategic plan into a prioritized set of programs happens during the programming step. This phase takes the strategic guidance and capability needs identified in planning and develops concrete program proposals, weighing options and trade-offs within the available resources. The output is a prioritized portfolio of programs, typically documented in the Program Objective Memorandum and the Future Years Defense Program, which specifies what will be funded and in what order over multiple years. Budgeting then assigns dollar amounts to those programs, and execution carries them out. So the programming phase is the one that converts strategy into an ordered, fundable set of programs.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy